Every Project is unique and requires unique solutions.  KANE Industries LLC thoroughly reviews the entire scope during the pre-bid discussion to develop a cost and schedule that is reliable for all parties.  Likewise, we execute that scope aligned with safety, cost, and schedule elements with clear progress communication.  Listed below are just some of the Project have completed or are current executing to completion.

Project
Details
Summary

Bible School Historical Renovations

Pall Mall, TN

Status:  Complete

Safety

0 LTI/RWI/MTI, 0 FA, 0 NM

Days

90

Personnel

6

Structural verification and remodeling of the historical Alvin York State Park Bible School building. Verification of structural integrity of Grist Mill building indicated insufficient lateral framing supports to allow for conventional remodel practices. Civil shoring of lower foundation of structure. Installation of underground drainage system to direct water away from foundation. Remodeling of siding, roof, roof ridge, gutters, painting, and ceiling replacement.

Fall Creek Fall Renovation Project 

Falls Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

0 LTI/RWI/MTI, 1 FA, 2 NM

Days

45

Personnel

10

Remodeling of three (3) Park residences and seven (7) Park commercial buildings in multiple locations with multiple work fronts.  Remodeling to include executing demolition of exterior framed walls, siding, and guttering. Installation of new exterior wall frames, siding, guttering, soffit, facia, windows and painting of all installed material.

Grist Mill Historical Project

Alvin York State Park, Pall Mall, TN

Status: Complete

Safety

0 LTI/RWI/MTI, 0 FA, 0 NM

Days

50

Personnel

6

Structural verification and remodeling of the historical Alvin York State Park Grist Mill building. Verification of structural integrity of Grist Mill building indicated insufficient lateral framing supports to allow for conventional remodel practices. A non-standard execution sequence had to be created whereby replacement of 10 sqft section in a sixty (60) foot working at height environment.   

Cabin Chimney Renovation Project

Falls Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

0 LTI/RWI/MTI, 1 FA, 2 NM

Days

30

Personnel

6

Renovating twelve (12) Park Guest Cabins, two (2) Park Guest service buildings, and one (1) Park Guest large cabin complex chimney systems.  Setting up safe working-at-height areas (40+ feet above the ground), masonry cleaning and surface preparation, and application of mason sealant to prevent water intrusion on structures that are 20+ years of age.

Western TN Storage Project

Alvin York State Park, Pall Mall, TN

Status: Complete

Safety

Due to mobilize

Days

124

Personnel

6

Procure, erect, commission, and handover of fourteen (x14) steel storage facilities for the State of Tennessee - Department of Health.  Requiring the procurement of material, transport to site, civil preparation, steel erection, steel and carpentry finishings at fourteen separate locations.

Harpath State Park Project

Falls Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

Due to mobilize

Days

26

Personnel

6

Installation of boat launch system for the Hapreth State Park.  Required civil preparation, formation of multiple embankments, rip-rap installation, lifting/rigging/placement of pre-cast members, carpentry/finishing.

Lake Site Project

Fall Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

Due to mobilize

Days

30

Renovation of Commercial building with replacement of damaged roofing sections, doors, frames, garage, and finishing elements. ​

Personnel

6

Mississippi St. Chattanooga Home Project

Falls Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

Days

16

0 LTI/RWI/MTI, 1 FA, 2 NM

Surface preparation, mold conditioning, hydraulic surface cleaning, and sealant application of residential flooring system. ​

Personnel

3

Fall Creek Falls Commercial

Fall Creek Falls State Park, Pikeville, TN

Status: Complete

Safety

0

Days

30

Personnel

12

Commercial renovations of the Fall Creek Falls Nature Center.  Removal of primary entry point and installation of ADA automatic door system.  Removal of exterior wall/window area and installation of ADA automatic door system.  Installation of a connecting concrete waiting area and walk way to connect with existing walk way.  All work included civil conditioning and water management, electrical installation, stucco siding, and gutters.